A Noise and Vibration Checklist for Newbuilding Sea Trials

A useful pre-delivery sea-trial measurement programme connects every test point to an operating condition, instrument channel, acceptance clause, witness and corrective decision before the vessel leaves the berth.

1. Convert the specification into a measurement-and-decision matrix

FieldDefine before trialFailure avoided
RequirementContract, rule, approved specification, maker criterion or diagnostic objective.Comparing a result against the wrong or assumed limit.
Test pointStable ID, deck/frame/space, axis, height and mounting.Unrepeatable retest and disputed location.
Operating stateSpeed/RPM, pitch, machinery combination, load, HVAC, sea and weather.Mixing results collected under different conditions.
EvidenceQuantity, bandwidth, duration, processing, witness and raw-data retention.A summary number that cannot be audited.
Decision ownerYard, owner, designer, maker, class/flag or another reviewer.Testing without an agreed closure route.

2. Use a trial-readiness gate before sailing

  • Approved trial agenda, measurement specification and latest drawings.
  • Test-point schedule physically accessible and safely prepared.
  • Instrumentation, channels, cables, power, time synchronisation and calibration verified.
  • Machinery tags, RPM/load/pitch signals and bridge/engine-room communications available.
  • Known defects, temporary equipment, incomplete insulation and open punch items declared.
  • Weather/sea-state limits, route, steady runs, turning time and repeat-run allowance agreed.
  • Witnesses and preliminary-result decision process confirmed.
Commercial safeguard: a “sea-trial survey” is not one universal package. Quote the named measurements, operating points, deliverables and acceptance basis.

3. Freeze each operating plateau

Create one operating-condition record for every plateau. Record propulsion RPM, shaft/propeller state, controllable pitch, vessel speed and heading, displacement/draft, trim, generator and pump combinations, HVAC condition, doors/openings, water depth, wind, sea state and transient events. Mark the start and stop of every steady measurement interval on a common trial log.

For berth or harbour trials, separately record mooring arrangement, nearby operations and limitations. For in-service troubleshooting, include the complaint reproduction sequence rather than assuming the delivery test matrix will reproduce the defect.

4. Define onboard noise measurements precisely

ISO 2923:1996 describes techniques and conditions for measuring noise onboard vessels, including acceptance, monitoring and investigation uses. Where IMO MSC.337(91), class rules, flag requirements or the shipbuilding contract apply, the agreed edition, vessel applicability, spaces and operating conditions must be confirmed.

  • Identify accommodation, workspaces, machinery spaces and external positions required by the basis.
  • Declare sound quantity, duration, microphone position and treatment of transient events.
  • Record machinery/HVAC state and whether doors, hatches and windows are open or closed.
  • Separate statutory/code assessment from owner comfort targets and diagnostic measurements.

5. Separate habitability, machinery and structural vibration

DecisionMeasurement approachDo not substitute
HabitabilityOccupied-space axes, frequency weighting, duration and operating condition required by the selected basis.A machinery casing reading does not describe human vibration exposure.
Machinery conditionBearing/housing points, direction, speed/load, spectra, phase/order evidence as required.One overall value cannot diagnose every fault.
Structural responseDeck/bulkhead/foundation grid, axes, RPM run-up or steady states and response patterns.Do not apply a generic machinery limit to a hull panel.
Torsional behaviourDedicated shaft/rotational measurement and operating sweep under an agreed specialist scope.Linear accelerometers alone do not establish torsional stress.

ISO 20283-5:2016 provides guidance for measuring, evaluating and reporting vibration with regard to habitability on passenger and merchant ships within its stated applicability. Use the contractually selected standard and agreed limits for the actual vessel.

6. Preserve synchronised engineering evidence

Synchronise acquisition channels and the bridge/engine-room event log. Record instrument model, serial number, calibration, sensor orientation, mounting, sample rate, filters, integration/weighting and analysis settings. Retain raw files, not only screenshots or rounded tables.

When an event appears, note exact RPM/load/pitch and concurrent machinery changes. This allows correlation across noise, vibration, shaft, control and operational data and reduces speculative diagnosis.

7. Control deviations, failures and retests

EventImmediate recordClosure
Required condition not achievedActual state, reason, affected points and witness decision.Repeat, accept by agreement or document limitation.
Unexpected peak or complaintTime, point, axis, RPM/load, spectrum/time history and simultaneous events.Focused diagnostic run and corrective owner.
Instrument/channel issueChannel, duration, field check and affected data.Invalidate/repeat only the impacted evidence.
Corrective modificationExact change and configuration.Retest the same point and operating condition.

8. Deliver an acceptance-ready evidence package

  1. Vessel particulars, trial purpose and applicable document hierarchy.
  2. Approved matrix, drawings and test-point schedule.
  3. Operating-condition log and deviations.
  4. Instrumentation, calibration and acquisition settings.
  5. Results with units, axes, frequency ranges and processing.
  6. Pass/fail or evaluation status only against the agreed basis.
  7. Diagnostic findings clearly separated from formal acceptance.
  8. Punch items, corrective action, retest scope and unresolved limitations.

9. Class, flag and acceptance context

Class witnessing, flag/statutory compliance, owner acceptance, yard contract performance and maker commissioning are different review routes. For ABS-, BV-, CCS-, CRS-, DNV-, IRS-, KR-, LR-, ClassNK-, PRS-, RINA- or Türk Loydu-classed vessels and relevant flags, confirm the applicable rules, approved documents, witness points and supplier requirements with the attending parties. Project acceptance does not establish supplier-approval status. This guide does not claim approval or guaranteed acceptance.

Authoritative references

10. What to send for a measurement proposal

  1. Vessel type, principal particulars, yard and trial location/window.
  2. Contract specification, class/flag basis and approved trial agenda.
  3. Required noise, vibration, machinery, PA/GA, HVAC or other measurements.
  4. GA, machinery layout, shaft/propulsion data and proposed test points.
  5. Witnesses, preliminary-result timing and final-report deadline.